You may have noticed the time counter on the main page. The launch date is primarilly set for May 16th 2009. thats 499 days..
New Years day managed to get a few hours to make the roof bits and make the girders for the aft roof.
Aft Cabin roof with backing strips fitted
The Boat so far.
Front Loader hired today, not cheap but the only way to lift the bits now.
Today the complete welding plant landed in the aft cabin,
it will stay onboard for the next few months as the sides are too high for it to stay on the ground.
Soon my lawns can grow grass instead of having tons of metal scattered over them.
Swim deck placed and tacked in place.
The extra bit is an extension I have specified in the cutting of the kit.
the underneath will follow the rub rail all round.
I intend to incorporate a swim ladder into it.
Inside view of the aft curved back.
Transom to go in next.