20th June 2008
Welcome back!. well truth be known, I got fed up of setting deadlines only to see them dashed by weather or work. Its over a month since I have posted.
So what has happened.....
The Keel is 90% finished
The AFT cabin is 100 finish wellded on the inside
The Engine room needs a day or 2 to be finished on the inside
The salon inside walls are fully finished..!
and the whole front end of the boat is 95% welded on the inside
In the last 2 days we got the top bullwark strips fitted and it realy straightened out the tops of the side walls of the boat.
All the walkways are fully welded and also the top roof of the foredeck.
Essentially theres about 4 days and the inside of the hull will be finished.
It will take a week to do the outside.
Keel finished.
Aft side wall
Fully lined up and welded
Transom ready for outside welding
As it stands there are 2 areas on the inside that havent been welded to let the rain out!
No comments:
Post a Comment