11/25/07

22 + 25th Nov 2007

Progress under way again, 6 hours on Thursday to finish the Aft cabin floor and get the frames 9 +10 in (5 more to go)

2 hours on Saturday fitting the frame tops 5-8



Forward of the engine bay stringers



Its size is really starting to show.


Today
added the aft frames 1-4 tops.

The side stringers and the frame stiffeners to be fitted next.

I also need to sort out acess to the hull from the rear as the sides will be impossible very soon.

Weather permitting , next work on tuesday, weds this week.